Deliver · Date-back Planner (Demo)
Pick an opening date; we calculate the milestones backwards. Export a real ICS file.
Project Basics
Used in calendar titles and file name.
Milestones
Opening on 2025-12-31 → 12 milestones
| Milestone | Offset | Date | Owner |
|---|---|---|---|
| Quotes Window Closes | -90 d | 2025-10-02 | Estimator |
| Samples Due | -75 d | 2025-10-17 | Vendor |
| Shop Drawings Due | -60 d | 2025-11-01 | Vendor |
| Brand Review Cutoff | -52 d | 2025-11-09 | Reviewer |
| 30% Deposit Due | -50 d | 2025-11-11 | Owner |
| Ship | -28 d | 2025-12-03 | Logistics |
| Land / Receive | -21 d | 2025-12-10 | Logistics |
| 70% Deposit Due | -20 d | 2025-12-11 | Owner |
| Install Start | -14 d | 2025-12-17 | Installer |
| Install Complete | -3 d | 2025-12-28 | Installer |
| Punch List Complete | -1 d | 2025-12-30 | PM |
| Opening | 0 d | 2025-12-31 | GM |